Construction of Road Chungi no. 11 to Village Ali Khan (Bypass Road)

Clients:
C&W
Scope of Services:
F, S, D,Q, C
Scope of work:
5no bridges at different locations
Timeframe:
Completed
Location:
Haripur

Construction of Road from Chungi No. 11 to Village Ali Khan (Bypass Road) – Haripur

Project Details

  • Client: Communication & Works (C&W), Haripur
  • Project Start Date: January 7, 2021
  • Project Completion Date: March 15, 2021
  • Total Project Cost: 30 million PKR
  • Bid Amount: 1.51 million PKR
  • Scope of Work: Foundation, Superstructure, Drainage, Quality Control, Construction (F, S, D, Q, C)
  • Contractor Type: Single Firm
  • Project Features:
    • Road Length: Designed to connect Chungi No. 11 to Village Ali Khan
    • Bridges: 5 bridges at different locations along the bypass road
    • Surface Type: Asphalt-paved road for improved durability and traffic flow
    • Function: Provides an alternate bypass route to reduce congestion in Haripur

Project Overview

The Chungi No. 11 to Village Ali Khan Bypass Road project was developed to enhance regional connectivity and provide a more efficient route for vehicles and pedestrians. This road plays a vital role in reducing traffic congestion within the city and offering a faster, more direct route for travelers.

A critical aspect of the project was the construction of five bridges at different locations along the bypass road. These bridges were necessary to cross water bodies, natural drains, and low-lying areas, ensuring an uninterrupted and smooth transportation corridor.

The project involved road construction, bridge design, foundation work, asphalt paving, and safety measures, ensuring high-quality infrastructure that meets national engineering standards.


Key Challenges in Construction

1. Terrain and Site Conditions

  • The project site included uneven terrain, requiring land leveling, soil compaction, and drainage solutions before road construction.
  • Water crossings at multiple locations made bridge placement and foundation stability crucial for long-term durability.

2. Bridge Engineering and Structural Integrity

  • The five bridges had to be designed for load-bearing capacity, flood resistance, and long-term durability.
  • Pier foundation construction was challenging in areas with a high water table and required extra reinforcement.

3. Traffic Management and Public Impact

  • The road construction affected local commuters and businesses, requiring an efficient traffic diversion plan.
  • Public concerns about access to residences and markets were addressed through community engagement and alternative routes.

4. Material and Logistics Challenges

  • Ensuring the availability of high-quality asphalt, cement, and steel in a short project timeline was challenging.
  • Transporting heavy machinery for road grading, paving, and bridge construction required coordination with local authorities.

5. Weather and Environmental Factors

  • Unpredictable rainfall and temperature fluctuations affected concrete curing times and road surfacing schedules.
  • Environmental considerations, including erosion control and water drainage planning, were integrated into the design.

Project Outcomes and Benefits

1. Enhanced Road Connectivity

  • The bypass road provides a direct and efficient connection between Chungi No. 11 and Village Ali Khan, reducing travel time.

2. Reduced Traffic Congestion in Haripur

  • By diverting traffic away from crowded urban areas, the new road helps improve traffic flow and safety.

3. Safe and Durable Bridges

  • The five bridges ensure year-round accessibility, preventing road closures due to flooding or poor terrain conditions.

4. Boost to Local Economy

  • Easier transportation enhances trade, commerce, and agricultural activities, benefiting local businesses and residents.

5. Sustainable Infrastructure Development

  • High-quality asphalt surfacing and reinforced bridge structures ensure long-term durability with minimal maintenance.

Conclusion

The Chungi No. 11 to Village Ali Khan Bypass Road project was successfully completed, despite logistical, environmental, and structural challenges. The construction of five bridges along the road ensures uninterrupted traffic flow, improving regional connectivity, trade, and public convenience. This infrastructure project significantly contributes to Haripur’s development by offering a safer, faster, and more efficient transportation network.